The stage of preparatory work for the execution of section 3

#stage #preparatory #work #execution #section

Important information about the stage of works for the start of the execution of section 3 of the A1 highway, Sibiu-Pitesti.

The stage of preparatory works for the start of the execution of section 3 of the A1, Sibiu-Pitesti, would be at 70-80%.

Section 3 of the A1 Sibiu-Pitesti, ready for construction

According to DRDP Craiova, the project is in a good situation Deforestation outside the forest fund is 100% done, and deforestation in the national forest fund is 62% done. The realization of the technical project for obtaining the AC is 75%, the deadline for delivery is until April 15, 2024. Archaeological studies, field studies and demining operations have been carried out in proportion to 100%. Agreements and approvals were obtained, in order to issue the Building Authorization. Two site organizations have been completely set up, with concrete stations and buildings for workshops and offices to be installed, according to the DRDP Craiova press release published on Facebook.

A segment of the Sibiu – Pitesti Highway could be inaugurated in 2024

Significant progress is being made on the 30-kilometer stretch between Curtea de Argeș and Pitesti, where the first layer of asphalt is already being applied.

That development is encouraging transportation officials, suggesting the highway could be completed before the contract date of 2025.

“The works are progressing very well, they are somewhere at 55% progress”, Sorin Grindeanu declared in 2023.

“Daniela” tunnel

The first tunnel drilled on a Romanian highway was called “Daniela”. This tunnel, with a length of 1.3 kilometers, passes under Momaia Hill in Argeș County.

Also Read:  Here are the 21 projects that will impact your trips in the spring

During his visit to the construction site, the Prime Minister conveyed a significant message to the Austrian builder.

I think it is the first breakthrough after the communist period. The builder is progressing with the work and I would like to congratulate them. I firmly believe that if we had been in Schengen, you would have been even further ahead”, said Marcel Ciolacu. This tunnel is part of a ten kilometer stretch of highway located between Tigveni and Curtea de Argeș.